Gordon Drive Improvement Project

Project details

Castle Rock Water and the Public Works Department are making infrastructure improvements along Gordon Drive to address stormwater flows and minimize street flooding. The project entails the addition of stormwater infrastructure; water and sanitary sewer line modifications and replacement; and pavement reconstruction.

Iron Woman Construction has been awarded this contract.

Anticipated project completion

Final completion was scheduled for December 2019; however, additional relocation of private utility lines (electric, gas, phone and cable) has impacted this timeline. Iron Woman Construction will be remobilizing this winter to complete the storm drainage improvements once the private utility lines have been relocated. Remaining pavement and sidewalk replacement will commence upon completion of the storm drainage improvements. Please note that temperatures need to be above  50 degrees for final asphalt placement.

Updated: Nov. 25, 2019

Gordon Drive Reconstruction (Gordon Lane to Johnson Drive)

  • Water main and service line replacement is complete.
  • Sanitary sewer main and service line replacement is complete.
  • Storm sewer installation between Gordon Lane and 300 Gordon Drive is substantially complete.
  • Construction of the concrete intake structure and outfall is planned – pending relocation of private utility lines.
  • Concrete curb, gutter and sidewalk replacement is substantially complete.
  • Asphalt replacement is substantially complete. Asphalt millings have been placed as a temporary surface on all unpaved areas and will be monitored throughout the winter.

Lower Gordon Drive (south Valley Drive to Gordon Lane)

  • Water main and service line replacement is complete.
  • Sanitary sewer service line replacement is complete.
  • Concrete curb, gutter and sidewalk replacement is partially complete.
  • Concrete and asphalt will be completed following construction of the storm outfall. Asphalt millings have been placed as a temporary surface on all unpaved areas and will be monitored throughout the winter.

Upper Gordon Drive (Johnson Drive to north Valley Drive)

  • Water main and service line replacement is complete.
  • Sanitary sewer service line replacement is complete.
  • Concrete curb, gutter and sidewalk replacement is  complete.
  • Asphalt replacement is complete.

Cul-de-sacs (Gordon Lane, Gordon Place and Gordon Court)

  • Water main and service line replacement is complete.
  • Sanitary sewer service line replacement is complete.
  • Concrete curb, gutter and sidewalk replacement is substantially complete.
  • Asphalt replacement is complete.

Contact

For additional information, call Castle Rock Water at 720-733-6000, the Stormwater Hotline at 720-733-2235, or email us.

GordonDr - Site Map-11.19