Banner image with rendering of fire station

Interior Concrete Complete


As Castle Rock thrives, Castle Rock Fire and Rescue strives to maintain its level of service to the community. That's why a new fire station is being built in Crystal Valley. 

CRFD broke ground on the new station in September 2017. The station is expected to open in summer 2018. Here's an update.

Week of April 30


This week, the concrete of the 100-foot-long bays of the fire station was poured. This completes the interior concrete of the station!

The inner siding of the tower was started, and dry walling of the west wing continued.
The east roadway was prepared for concrete to be poured on Monday, May 14.

aerial view of new fire station at 100 feet
aerial view of new station at 200 feet
aerial view of new station from 150 feet on west side

About the new station

The new fire station will be located on north side of Crystal Valley Parkway, just east of the Crystal Valley Parkway bridge. The location was determined as part of the department’s research for the 2014-17 Fire Master Plan. 

To create the plan, Castle Rock Fire and Rescue analyzed the Town’s demographics and growth rate; percentages of build-out for area developments; and calls for service and responses to various areas throughout Town. The analysis indicated the next area of need is Crystal Valley. 

The new station is expected to open with 12 new staff members in summer 2018.  


Powered by CivicSend - A product of CivicPlus